Island Beach Wastewater Treatment Plant Demolition
General Services and Resident Engineering (GSRE)
TGW Engineering provided decommissioning and general services during construction for the demolition of the City of Venice 2 mgd Island Beach Wastewater Treatment Plant.
Services included:
Planning and Permitting
Design Plans and Specifications
Bidding
Project Management
Construction Performance Oversight and Resident Inspection
Record Drawings and Final Certification
City of Venice
East Side Wastewater Treatment Plant Project A Reuse Pipeline
General Services and Resident Engineering (GSRE)
TGW Engineering acted as the City of Venice agent and provided general services during construction for the installation of 10 miles of reuse pipe including jack and bore of I-75 corridor, 12 lift station rehabilitations, 3 master lift stations, 1 mile of transmission forcemain, and flow re-route from the Island Beach WWTP to service the City of Venice 3 mgd East Side Wastewater Treatment Plant Expansion.
Speciality type items of this work included Construction Manager at Risk contract, horizontal directional drilling, jack and bore under I-75, and major wastewater flow diversions and by-passes.
Services included:
Value Engineering Study and Recommendations
Contract Negotiations
Project Management
Construction Performance Oversight and Resident Inspection
Government Material Purchase Tracking for Tax Saving Purposes
Change Order, Pay Request Review and Negotiations
Record Drawings and Final Certification
TGW Engineering obtained and evaluated data and documentation relevant to information regarding the physical features of the wastewater plant to perform professional services to Phase the demolition work.
The project began with developing a plan to divert flow from the Island Beach Plant to the City’s expanded AWT facility. Upon switching flows, the old plant was decommissioned and cleaned. Asbestos materials were removed while TGW Engineering finalized demolition and civil plans and specifications. The demolition and construction work was divided into two separate contracts for scheduling purposes.
One of the design challenges was the development of demolition specifications for three Crom pre-stressed concrete tanks. Old record drawings were found to assist with describing existing conditions for safety considerations.